Why we give you a later delivery date than the manufacturer

It happens regularly, and the mood on the phone is always the same: »The manufacturer says week 40, you say week 41 – why are you slower?« The short answer: We aren’t slower. We’re simply more honest about what the date actually means. I’m writing down the long answer here because it might save you an awkward email to your end customer on your next project.

A manufacturer’s delivery date is generally a dispatch date. It tells you when the goods leave the manufacturer – not when they arrive with us, and certainly not when they reach your customer. In between, there is transport, goods receipt, inspection, warehousing, order picking and the journey to you. We’re not talking about weeks, but we are talking about days – and those days determine whether your rollout starts on Monday or the Monday after.

Imagine if we simply passed the manufacturer’s date on to you. You pass it on to your end customer, who schedules staff, books the technician and informs the branches. The goods are then dispatched on time – but they haven’t arrived yet. Technically, nobody lied. In practice, twelve people are standing in a branch looking at the empty space where the pallet was supposed to be. Who pays for the technician who made the journey for nothing? Not the manufacturer. Not us. You.

That’s why we give you the date when we realistically expect to be able to hand the goods over to you. It’s later than the manufacturer’s date, sometimes frustratingly so, and it certainly won’t win any popularity contests on the phone. But it’s a date you can pass on to your customer without ending up embarrassed in the end. A distributor who gives you the earlier date isn’t selling you faster delivery. They’re selling you peace of mind – until the day the goods fail to turn up.

Now for the uncomfortable part: Our date doesn’t always hold either. Manufacturers postpone deliveries, containers are delayed, a batch fails inspection. I’ve written before about how we’ve committed to dates only for the manufacturer to throw those plans into disarray afterwards – and that still happens. The difference isn’t whether a date gets pushed back, but when you find out about it. With us, you find out as soon as we do. Not on the delivery date, when you have to ask.

And here’s a piece of advice that costs you nothing: For every project tied to a fixed date, tell us the date – not just the quantity. »We need 60 devices« is an order. »We need 60 devices, configured and ready to go on 3 November because that’s when the branch opens« is a project. With a project, we have the opportunity to order earlier, reserve stock or tell you in good time if things are going to be tight. I’ve already written about EOL with advance warning; this is the same principle on a smaller scale: The earlier we talk, the more options we have.

Ultimately, a delivery date is neither a wish nor an estimate, but a commitment that someone else bases their planning on. We’d rather give you a date you don’t like today than one that leaves you having to explain yourself three weeks from now.

So remember: »An early date that doesn’t hold is slower than a later one that does.«
 